—PAGE35—XM市XX橋改造工程項(xiàng)目橋梁工程監(jiān)理細(xì)則XX建設(shè)有限公司XX橋改造工程項(xiàng)目監(jiān)理部二00G年三月XM市XX橋改造工程項(xiàng)目橋梁工程部分總監(jiān)理工程師:(簽字)(日期)專業(yè)監(jiān)理工程師:(簽字)(日期)XX建設(shè)有限公司XX橋改造工程項(xiàng)目監(jiān)理部

目錄工程概況··········································1施工工藝及質(zhì)量監(jiān)理流程圖··························1工程材料及設(shè)備程序······························1橋位及孔樁施工放樣程序··························2樁基礎(chǔ)工藝序圖··································2承臺工藝程序圖··································3墩臺施工工藝程序································4蓋梁施工工藝程序圖······························5預(yù)應(yīng)力變截面箱型梁施工工藝程序圖················6橋面鋪裝工藝程序································7橋頭搭板工藝程序································8橋梁工程完工驗(yàn)收程序圖·························9監(jiān)理工作控制要點(diǎn)及目標(biāo)值·························10控制要點(diǎn)·······································10目標(biāo)值·········································10鉆孔灌注樁基礎(chǔ)································10承臺··········································11鋼筋、模板成型與安裝··························12墩臺及蓋梁····································13預(yù)應(yīng)力變截面連續(xù)箱梁··························13⑥、預(yù)應(yīng)力筋加工及張拉····························14⑦、橋面瀝青砼鋪裝································15⑧、人行道鋪裝····································15⑨、欄桿安裝······································16質(zhì)量保證資料檢驗(yàn)·······························17施工方法及要求···································18鉆孔灌注樁····································18承臺、墩臺身及蓋梁鋼筋砼施工··················19預(yù)應(yīng)力變截面連續(xù)箱梁··························19橋面鋪裝······································20監(jiān)理工作方法及措施·······························21監(jiān)理程序控制···································21現(xiàn)場質(zhì)量控制···································22資料管理·······································23橋梁工程使用主要表格···························23

工程概況:XX橋位于XM市中心GAO東路橫跨GTO湖上的一座橋梁。原有橋梁建于1985年,在目前大型載重車輛行駛下,橋面振動很大,伸縮縫嚴(yán)重破壞,橋臺下沉產(chǎn)生錯(cuò)臺,橋面有多處橫向裂縫。鑒于目前狀況,必須改造,將舊橋拆除重新建橋新橋梁特點(diǎn)是:下部構(gòu)造采用:橋臺采用Φ120鉆孔灌注樁28根,橋墩Φ150鉆孔灌注樁12根,樁長32-41米不等;鋼筋砼墩臺身,上部構(gòu)造采用3跨30+45+30米鋼筋砼預(yù)應(yīng)力變截面連續(xù)箱梁。橋面凈寬40米,其中設(shè)28米寬的行車道,兩側(cè)各設(shè)6米的人行道,箱梁采用C50#砼,橋面鋪裝采用SMA改性瀝青砼,厚10cm,兩端接線在原有基礎(chǔ)上改造15000m2

施工工藝及質(zhì)量監(jiān)理流程圖工程材料及設(shè)備程序承包人填報(bào)工程材料及設(shè)備報(bào)審表承包人填報(bào)工程材料及設(shè)備報(bào)審表監(jiān)理工程師檢查審查報(bào)驗(yàn)資料符合要求與否在報(bào)驗(yàn)單上簽字同意在指定部位使用附表:產(chǎn)品出廠合格證、數(shù)量清單、質(zhì)量證明文件、自檢結(jié)果在報(bào)驗(yàn)單上簽字不同意材料設(shè)備進(jìn)場橋位及孔樁施工放樣程序監(jiān)理程序施工程序現(xiàn)場檢查符合現(xiàn)場檢查符合橋位及水準(zhǔn)點(diǎn)復(fù)測孔樁位置復(fù)測及固定設(shè)置現(xiàn)場檢查固定樁位審檢簽字確認(rèn)施工放樣報(bào)驗(yàn)申請表報(bào)開工報(bào)告附施工組織設(shè)計(jì)及方案、工程材料及設(shè)備報(bào)檢現(xiàn)場檢查固定樁位經(jīng)常自檢、自查樁基礎(chǔ)工藝序圖監(jiān)理程序施工程序檢查符合要求檢查符合要求鉆機(jī)定位、吊錘對中、埋護(hù)筒、測護(hù)筒頂標(biāo)高開鉆報(bào)送原材料及砼配合比、機(jī)具、人員表審查原材料、砼配合比鉆進(jìn)成孔自檢合格制鋼筋籠旁站確認(rèn)孔深、孔位、孔徑,符合設(shè)計(jì)要求時(shí)決定終孔清孔、下鋼筋籠焊接埋設(shè)超生波管、下導(dǎo)管再清孔、自檢合格、檢查鋼筋籠、泥漿、沉淀層厚、導(dǎo)管等澆筑水下砼旁站、檢查坍落度、取樣做試塊破樁頭、做超生波檢測砼試塊檢查中間交工證書承包人報(bào)請分項(xiàng)工程驗(yàn)收及中間交工證書監(jiān)理抽檢與確認(rèn)監(jiān)理評定分項(xiàng)工程質(zhì)量等級制作試塊養(yǎng)護(hù)準(zhǔn)予中間計(jì)量中間計(jì)量表

承臺工藝程序圖監(jiān)理程序施工程序檢查放樣及原材料、配合比檢查放樣及原材料、配合比施工放樣、原材料及砼配合比分項(xiàng)工程開工報(bào)告(附計(jì)劃表、材料報(bào)單)審查開工報(bào)告破樁頭、測樁頭標(biāo)高檢查樁頂標(biāo)高及平面位置模板、鋼筋制作安裝墩臺預(yù)埋鋼筋、自檢合格檢查模板、鋼筋等澆筑承臺砼旁站、測坍落度、做砼試塊拆模、養(yǎng)護(hù)、自檢外部尺寸合格檢查外形尺寸及外觀制作砼試塊中間交工證書承包人報(bào)請分項(xiàng)工程驗(yàn)收及中間交工證書監(jiān)理抽檢與確認(rèn)監(jiān)理評定分項(xiàng)工程質(zhì)量等級準(zhǔn)予中間計(jì)量中間計(jì)量表樁基超聲波檢測合格墩臺施工工藝程序監(jiān)理程序施工程序?qū)彶樵牧?、砼配合比審查原材料、砼配合比施工放樣、原材料及砼配合比分?xiàng)工程開工報(bào)告審查開工報(bào)告墩臺鋼筋安裝、自檢合格檢查鋼筋焊接及骨架尺寸立模、測量墩臺頂標(biāo)高檢查墩臺頂高程及模板尺寸澆筑墩臺砼旁站、測坍落度、做砼試塊外觀尺寸檢查監(jiān)理監(jiān)督檢查確認(rèn)制作砼試塊中間交工證書承包人報(bào)請分項(xiàng)工程驗(yàn)收及中間交工證書監(jiān)理抽檢與確認(rèn)監(jiān)理評定分項(xiàng)工程質(zhì)量等級準(zhǔn)予中間計(jì)量中間計(jì)量表拆模養(yǎng)護(hù)返工修補(bǔ)附件:1、施工組織設(shè)計(jì)2、原材料機(jī)具及人員上崗證3、砼配合比、鋼材、水泥檢驗(yàn)報(bào)告蓋梁施工工藝程序圖監(jiān)理程序施工程序監(jiān)理檢查底模板標(biāo)高監(jiān)理檢查底模板標(biāo)高放樣、報(bào)原材料砼配合比鋼筋制作、安裝自檢合格、側(cè)模制作安裝檢查模板鋼筋及預(yù)埋筋澆筑蓋梁砼旁站、測坍落度、做砼試塊拆側(cè)模、養(yǎng)護(hù)砼強(qiáng)度達(dá)到設(shè)計(jì)要求拆支架模板返工修補(bǔ)外觀尺寸檢查砼試塊制作中間交工證書承包人報(bào)請分項(xiàng)工程驗(yàn)收及中間交工證書監(jiān)理抽檢與確認(rèn)監(jiān)理評定分項(xiàng)工程質(zhì)量等級準(zhǔn)予中間計(jì)量中間計(jì)量表搭支架、安裝底模預(yù)應(yīng)力變截面箱型梁施工工藝程序圖監(jiān)理程序施工程序?qū)彶橹Ъ?、底板審查支架、底板搭設(shè)支架、立底模、安支座施工放樣、預(yù)壓、測量檢查預(yù)拱度及高程施工放樣及原材料、砼配合比檢驗(yàn)申請表審批放樣、原材料分項(xiàng)工程開工報(bào)告(附計(jì)劃表、材料報(bào)單)審查開工報(bào)告安裝底模、側(cè)板鋼筋預(yù)應(yīng)力定位筋、穿波紋管檢查底板、鋼筋等安裝內(nèi)模及側(cè)模、橫隔梁鋼筋檢查模板安裝、鋼筋制作砼試塊中間交工證書承包人報(bào)請分項(xiàng)工程驗(yàn)收及中間交工證書監(jiān)理抽檢與確認(rèn)監(jiān)理評定分項(xiàng)工程質(zhì)量等級準(zhǔn)予中間計(jì)量中間計(jì)量表安裝頂板翼板鋼筋、錨墊板鋼筋檢查模板、鋼筋澆筑砼旁站、測坍落度、做砼試塊拆側(cè)模、內(nèi)模、養(yǎng)護(hù)、清理孔道返工修補(bǔ)外觀尺寸檢查檢查外觀尺寸砼強(qiáng)度達(dá)到90%穿鋼絞線張拉監(jiān)督張拉并記錄壓漿、封錨監(jiān)督壓漿并記錄橋面鋪裝工藝程序監(jiān)理程序施工程序?qū)彶樵牧?、砼配合比審查原材料、砼配合比?bào)原材料砼配合比開工報(bào)告(附進(jìn)度計(jì)劃、方案、機(jī)具、人員)審查開工報(bào)告鋪裝瀝青砼面層兩層(4+6cm)旁站檢查清理橋面及安裝伸縮縫鑿毛檢查伸縮縫安裝質(zhì)量澆筑C50鋼纖維砼封槽中間交工證書承包人報(bào)請分項(xiàng)工程驗(yàn)收及中間交工證書2、監(jiān)理抽檢與確認(rèn)3、監(jiān)理評定分項(xiàng)工程質(zhì)量等級準(zhǔn)予中間計(jì)量中間計(jì)量表橋頭搭板工藝程序監(jiān)理程序施工程序碾壓臺后填土密度達(dá)到95%碾壓臺后填土密度達(dá)到95%搭板下填土密度實(shí)驗(yàn)檢查檢查驗(yàn)收搭板下填土密實(shí)度搭板鋼筋、模板制作檢查搭板鋼筋、模板澆筑砼旁站、測坍落度、做砼試塊外觀及尺寸檢查外觀及尺寸檢查制作砼試塊中間交工證書承包人報(bào)請分項(xiàng)工程驗(yàn)收及中間交工證書監(jiān)理抽檢與確認(rèn)監(jiān)理評定分項(xiàng)工程質(zhì)量等級準(zhǔn)予中間計(jì)量中間計(jì)量表拆模、養(yǎng)護(hù)橋梁工程完工驗(yàn)收程序圖橋梁完工橋梁完工承包人交工驗(yàn)收自檢,并匯總開工報(bào)告、材料實(shí)驗(yàn)、砼強(qiáng)度試驗(yàn)、各工序質(zhì)量檢驗(yàn)單監(jiān)理抽檢合格,并匯總備齊簽發(fā)中間交工證書交工驗(yàn)收自檢合格,并匯總開工、試驗(yàn)、檢驗(yàn)單,填報(bào)中間交工證書計(jì)量,可以進(jìn)行下一道工序監(jiān)理抽檢,并審查承包人匯總的開工申請,材料強(qiáng)度試驗(yàn)及各工序檢驗(yàn)單監(jiān)理工作控制要點(diǎn)及目標(biāo)值控制要點(diǎn):①、認(rèn)真閱讀熟悉圖紙、規(guī)范、規(guī)程及有關(guān)資料,編制施工方案及計(jì)劃,檢查各項(xiàng)準(zhǔn)備工作。②、施工放樣關(guān)系到橋位、孔樁的正確與否,要認(rèn)真復(fù)測檢查。③、工程材料、砼配合比的設(shè)計(jì)及機(jī)具、供電、安全方面、人員上崗條件是必須檢驗(yàn),檢查合格后才能開工。④、按照設(shè)計(jì)及規(guī)范要求,認(rèn)真組織施工。特別是鉆孔灌注樁的施工,預(yù)應(yīng)力箱梁的施工,稍有差錯(cuò)會造成返工。⑤、認(rèn)真抓好各種試驗(yàn)及資料工作。⑥、各工序必須按照施工工藝程序辦理,上一道工序不合格不得進(jìn)行下一道工序。⑦、鉆孔灌注樁砼嚴(yán)禁有夾層和松散層,鋼筋制作安裝必須符合設(shè)計(jì)及施工規(guī)范的要求,嚴(yán)格掌握砼的坍落度,必須符合砼配合比的要求,墩臺要控制好標(biāo)高及外形尺寸,表觀良好,預(yù)應(yīng)力連續(xù)箱梁必須控制預(yù)拱度、砼質(zhì)量及各種標(biāo)準(zhǔn)。橋面鋪裝必須控制好伸縮縫的安裝及橋面平整度,兩端接線的銜接,不允許跳車,欄桿安裝必須美觀牢固。目標(biāo)值:鉆孔灌注樁基礎(chǔ):保證項(xiàng)目:原材料必須符合設(shè)計(jì)及施工規(guī)范要求。沉淀層不得大于5cm,孔深、孔徑、孔位及樁頭必須符合設(shè)計(jì)要求,孔中砼強(qiáng)度不得小于設(shè)計(jì)規(guī)定,鋼筋籠制作安裝正確。現(xiàn)場檢測評定按照下表操作:鉆孔灌注樁序號項(xiàng)目允許偏差檢驗(yàn)頻率檢驗(yàn)方法范圍點(diǎn)數(shù)1△砼抗壓強(qiáng)度按TJT071-98附錄D每根樁1必須符合附錄D的規(guī)定2△孔徑不小于設(shè)計(jì)規(guī)定1用探孔器檢驗(yàn)3△孔深+50mm01用測繩量測4樁位順橋縱軸線方向50mm1用尺量垂直橋縱軸方向50mm15沉淀厚度不大于50mm1開始灌注砼前用測繩量6清孔后泥漿量相對密度<1.2孔中部1用儀器測量含砂率<4%孔中部1稠度18~20s孔中部1承臺:、保證項(xiàng)目:所用原材料及砼配合比必須符合設(shè)計(jì)及規(guī)范要求,不得有空洞、露筋現(xiàn)象出現(xiàn),鋼筋模板制作安裝正確。項(xiàng)次檢查項(xiàng)目規(guī)定值或允許偏差檢查方法及頻率檢查結(jié)果1△混凝土強(qiáng)度在合格標(biāo)準(zhǔn)內(nèi)按規(guī)定計(jì)算2斷面尺寸±30mm用尺量長寬高各2點(diǎn)3頂面高程±20mm用水準(zhǔn)儀測量4軸線偏差15mm用經(jīng)緯儀縱橫測量現(xiàn)場檢測評定按照下表操作:鋼筋成型與安裝序號項(xiàng)目允許偏差(mm)檢驗(yàn)頻率檢查方法范圍點(diǎn)數(shù)1受力鋼筋間距梁、柱、板±10每個(gè)構(gòu)筑物或構(gòu)件4在任意一個(gè)斷面連續(xù)量取鋼筋間(排)距,取其平均值計(jì)1點(diǎn)基礎(chǔ)、墩臺±204順高度方向配置兩排以上的間距±522螺旋筋、箍筋及構(gòu)造筋間距+0-205~10連續(xù)量取5檔,其平均值計(jì)1點(diǎn)3同一截面內(nèi)受拉鋼筋接頭截面積占鋼筋總截面積焊接不大于50%觀察綁扎不大于25%4保護(hù)層厚度墩、臺、基礎(chǔ)±10沿周邊檢查8處用尺量梁、柱、樁±5板、墻±3模板成型與安裝序號項(xiàng)目允許偏差(mm)檢查頻率應(yīng)測點(diǎn)數(shù)實(shí)測點(diǎn)數(shù)合格點(diǎn)數(shù)合格率%檢查方法范圍點(diǎn)數(shù)1相鄰兩板表面高低差刨光模板鋼板2每個(gè)構(gòu)筑物或構(gòu)件4用尺量不刨光模板42表面平整度刨光模板鋼板342米直尺量或楔形尺量不刨光模板53垂直度墻、柱0.1%H且≤62垂線或經(jīng)緯儀測4模內(nèi)尺寸基礎(chǔ)+10-203用尺量長寬高各1點(diǎn)梁板墻柱+4-55軸線偏位基礎(chǔ)154經(jīng)緯儀測縱橫各計(jì)2點(diǎn)墻5梁柱56預(yù)埋件、預(yù)留孔位置10用尺量

墩臺及蓋梁、保證項(xiàng)目:原材料及砼配合比必須符合設(shè)計(jì)及施工規(guī)范要求,砼強(qiáng)度不得小于設(shè)計(jì)規(guī)定,外表不得有空洞露筋,鋼筋模板制作安裝正確。現(xiàn)場檢測評定按照下表操作:鋼筋成型與安裝允許偏差(同上表)項(xiàng)次檢查項(xiàng)目規(guī)定值或允許偏差檢查方法及頻率檢查方法范圍點(diǎn)數(shù)1△混凝土強(qiáng)度按砼強(qiáng)度驗(yàn)收標(biāo)準(zhǔn)評定2斷面尺寸寬±20mm每個(gè)構(gòu)筑物3用鋼尺丈量高±20mm3用鋼尺丈量3軸線偏差縱向10mm1拉線用鋼尺量橫向10mm1拉線用鋼尺量4支座位置5mm各支座測距儀測5支座頂面高程±5mm各支座水準(zhǔn)儀測6預(yù)埋件位置5mm全部用鋼尺丈量

預(yù)應(yīng)力變截面連續(xù)箱梁、保證項(xiàng)目:原材料及砼配合比必須符合設(shè)計(jì)及施工規(guī)范要求,外表不得有空洞露筋,預(yù)應(yīng)力筋及非預(yù)應(yīng)力鋼筋制作安裝正確?,F(xiàn)場檢測評定按照下表操作:檢查項(xiàng)目規(guī)定值或允許偏差(mm)檢查頻率合格率檢查方法范圍點(diǎn)數(shù)△砼強(qiáng)度按砼強(qiáng)度驗(yàn)收標(biāo)準(zhǔn)評定預(yù)應(yīng)力連續(xù)箱梁斷面尺寸支座處+8-5每個(gè)構(gòu)件5用鋼尺丈量跨中處+8-55用鋼尺丈量1/4跨處+8-55用鋼尺丈量預(yù)拱度L/6005拉線用鋼尺量長度+0-103用鋼尺丈量軸線偏位103平整度8多處用2米直尺量支座高差2每個(gè)支座水準(zhǔn)儀測

⑥、預(yù)應(yīng)力筋加工及張拉保證項(xiàng)目:預(yù)應(yīng)力筋及錨具必須符合國家現(xiàn)行標(biāo)準(zhǔn)要求,張拉設(shè)備必須經(jīng)國家認(rèn)定機(jī)構(gòu)檢驗(yàn),管道安裝牢固、接頭密合,彎曲圓順,錨墊板平面必須與孔道軸線垂直。壓漿密度、水泥漿符合、要求。現(xiàn)場檢測評定按照下表操作:項(xiàng)目檢查項(xiàng)目規(guī)定值或允許偏差檢查方法及頻率檢查結(jié)果1管道坐標(biāo)(mm)梁長方向30mm抽查30%每根10個(gè)點(diǎn)梁高方向10mm2管道間距(mm)同一排10mm抽查30%每根5個(gè)點(diǎn)上下層10mm3△張拉應(yīng)力值符合設(shè)計(jì)要求查張拉記錄4張拉伸長率±6%查張拉記錄5斷絲、滑絲數(shù)量鋼束每束1根且每斷面不超過鋼絲總數(shù)的1%查張拉記錄鋼筋

⑦、橋面瀝青砼鋪裝:保證項(xiàng)目:瀝青混合料的礦料質(zhì)量及礦料級配應(yīng)符合設(shè)計(jì)要求及施工規(guī)范的規(guī)定??刂茷r青混合料的加熱溫度,不結(jié)團(tuán)成塊、無花白,要均勻一致。攤鋪平整度及壓實(shí)度達(dá)到設(shè)計(jì)要求?,F(xiàn)場檢測評定按照下表操作:項(xiàng)次檢查項(xiàng)目規(guī)定值或允許偏差檢查方法及頻率檢查結(jié)果1△壓實(shí)度%95%每200m、每車道2△平整度σmmIRI(m/Km)1.22.0平整度儀、全線每車道連續(xù)每100米計(jì)算σ、IRI(m/Km)最大間隙5.03米直尺、每200m2103彎沉值0.01mm≤竣工驗(yàn)收彎沉值按照附錄檢查4抗滑摩擦系數(shù)符合設(shè)計(jì)要求構(gòu)造深度符合設(shè)計(jì)要求鋪砂法測5厚度(mm)代表值總厚度-8上面層-4按照附錄H檢查每200m每車道1點(diǎn)極值總厚度-15上面層-8按照附錄H檢查每200m每車道1點(diǎn)6中線平面偏位(mm)20用經(jīng)緯儀縱橫測量7縱斷面高程(mm)±10mm水準(zhǔn)儀測200m4處8寬度(mm)±20mm用鋼尺量每200m4處9橫坡(%)±0.3水準(zhǔn)儀測200m4處⑧、人行道鋪裝:⑴、保證項(xiàng)目:人行道板安裝必須牢固、平穩(wěn)。⑵、現(xiàn)場檢測評定按照下表操作:項(xiàng)次檢查項(xiàng)目規(guī)定值或允許偏差檢查方法及頻率檢查結(jié)果1人行道邊緣平面偏位5mm30m拉線檢查2縱向高程+10mm-0每100米用水準(zhǔn)儀測3處3接縫兩側(cè)高差2mm用水準(zhǔn)儀測量4橫坡(%)5每100米用3m直尺測3處5平整度(mm)5每100米用3m直尺測3處

⑨、欄桿安裝:保證項(xiàng)目:欄桿不得有斷裂或彎曲現(xiàn)象,必須牢固美觀。現(xiàn)場檢測評定按照下表操作:項(xiàng)次檢查項(xiàng)目規(guī)定值或允許偏差檢查方法及頻率檢查結(jié)果1柱平面位置4mm每5根柱拉線檢查2扶手平面偏位3mm30m拉線檢查或用經(jīng)緯儀檢查3柱頂面高差4mm用水準(zhǔn)儀抽查20%4柱縱橫垂直度4mm用尺抽查20%5相鄰扶手高差5mm用尺抽查20%

質(zhì)量保證資料檢驗(yàn)按下表評定:序號檢查內(nèi)容檢查重點(diǎn)檢查情況標(biāo)準(zhǔn)分實(shí)得分1主體結(jié)構(gòu)技術(shù)質(zhì)量實(shí)驗(yàn)資料樁檢測、砼強(qiáng)度、砼試塊強(qiáng)度222原材料試驗(yàn)、預(yù)制件資料、合格產(chǎn)品證明砂、石、水泥、鋼材、瀝青檢測資料,計(jì)量設(shè)備校核資料,主要外購件合格證223總體質(zhì)量綜合試驗(yàn)資料砼試塊強(qiáng)度匯總、鋼筋水泥檢測匯總124隱蔽工程驗(yàn)收單凡下道工序覆蓋部分的重點(diǎn)項(xiàng)目都要隱檢手續(xù)125工程質(zhì)量評定表分項(xiàng)、分部及單位工程質(zhì)量評定資料126質(zhì)量事故處理報(bào)告、處理、結(jié)案及時(shí)有市政質(zhì)監(jiān)站認(rèn)可0-67施工組織設(shè)計(jì)、技術(shù)交底有質(zhì)量目標(biāo)、措施落實(shí)情況、環(huán)保、文明施工、安全、節(jié)約及專項(xiàng)方案設(shè)計(jì)、審批完備、設(shè)計(jì)交底、施工交底齊備68洽商記錄、竣工圖洽商紀(jì)要、變更齊全,有編號,手續(xù)完整,竣工圖清晰完整,與實(shí)際符合,有配合比通知單及施工記錄109測量復(fù)核記錄控制點(diǎn)、基準(zhǔn)線、水準(zhǔn)點(diǎn)復(fù)核記錄,有測必復(fù)410合計(jì)100扣分原則:主體結(jié)構(gòu)資料按質(zhì)量檢驗(yàn)評定標(biāo)準(zhǔn)要求的檢驗(yàn)內(nèi)容和頻率,凡帶有“△”項(xiàng)目不合格或漏檢點(diǎn)數(shù)達(dá)到全部應(yīng)檢點(diǎn)數(shù)的1%扣3分,直到扣完為止。此項(xiàng)得分不足70%者資料評分為不合格。原材料合格證每缺一項(xiàng)或不合格視嚴(yán)重程度扣0.5-2分,合格證、質(zhì)保單、試驗(yàn)報(bào)告,原件可以復(fù)印,但必須蓋紅印。施工方法及要求鉆孔灌注樁:根據(jù)水文地質(zhì)情況,選準(zhǔn)施工方法、鉆孔順序及選擇機(jī)具設(shè)備。必須準(zhǔn)備充足的泥漿,使泥漿的各種指標(biāo)符合規(guī)范要求,才可以進(jìn)行鉆孔作業(yè)。鉆孔工作要一氣呵成,防止坍孔、漏水、鉆孔偏位或歪斜、卡鉆等。鋼筋籠制作準(zhǔn)確、牢固,焊接必須符合規(guī)范要求。吊裝入孔時(shí)不要碰壞孔壁。在灌注砼時(shí)要嚴(yán)防鋼筋籠上浮、位移。灌注水下砼時(shí),開始第一次灌注是否能成功地將導(dǎo)管內(nèi)的水壓出,并順利地埋導(dǎo)管口,形成導(dǎo)管中砼于孔樁中的泥漿的隔離,是決定灌注水下砼成敗的關(guān)鍵。因此,在開始灌注砼時(shí)應(yīng)特別注意到:第一盤拌料應(yīng)用高標(biāo)號砂漿堵塞導(dǎo)管上口,(導(dǎo)管口用圓形鋼板蓋住,上用鋼絲繩吊入卷揚(yáng)機(jī)上),然后再將拌好的砼倒入漏斗直到裝滿為止。漏斗中要有充足砼量才能將導(dǎo)管下部埋置,阻止水侵入導(dǎo)管,1.2m樁徑不能少于2.0m。為了保證使導(dǎo)管下部能提升還需要多備兩盤料進(jìn)入料斗跟隨提蓋后倒入漏斗同時(shí)進(jìn)入導(dǎo)管直至樁底,若采用商品砼,砼運(yùn)輸車必須連續(xù)進(jìn)場灌注。隨時(shí)檢測孔中砼灌注高度,特別注意鋼筋籠變根數(shù)斷面底面時(shí)要漫進(jìn)鋼筋籠底2-3米時(shí)立即拆管,使埋管深度保持1米左右為安全,以防止鋼筋籠上浮。要等孔中砼強(qiáng)度達(dá)到設(shè)計(jì)強(qiáng)度的70%才能開孔作業(yè)旁邊鉆孔樁。要做好各種原始記錄資料。承臺、墩臺身及蓋梁鋼筋砼施工:模板工程:必須要有足夠的剛度、強(qiáng)度和穩(wěn)定性,符合設(shè)計(jì)要求及規(guī)范要求的各種規(guī)定。保證砼表面關(guān)滑、無麻面、漏漿及表面不平整。鋼筋工程:制作安裝必須符合設(shè)計(jì)及規(guī)范要求。焊接制品的機(jī)械性能必須符合鋼筋焊接及驗(yàn)收規(guī)范要求。電焊工必須持證上崗。砼工程:砼所用水泥、砂、石、水及外加劑必須檢驗(yàn),符合施工規(guī)范及設(shè)計(jì)要求才可使用。砼配合比、原材料的計(jì)量、攪拌、運(yùn)輸及養(yǎng)護(hù)必須符合規(guī)范要求。坍落度抽查及砼試塊制作、養(yǎng)護(hù)必須符合有關(guān)規(guī)定。做完整的資料記錄。預(yù)應(yīng)力變截面連續(xù)箱梁:除上述規(guī)定外,強(qiáng)調(diào)底模高程及預(yù)拱度必須符合設(shè)計(jì)要求,支架穩(wěn)固,保證不下沉。預(yù)埋件準(zhǔn)確牢固。另外砼強(qiáng)度必須達(dá)到設(shè)計(jì)的85%方可進(jìn)行張拉。橋面鋪裝:保證橋面鋪裝厚度,在鋪橋面前一定要測量橋面高程。安裝伸縮縫必須符合設(shè)計(jì)要求。鋪橋面SMA改性瀝青必須符合設(shè)計(jì)及施工規(guī)范規(guī)定。橋面要平整,并有一定的抗滑設(shè)施及保證在伸縮縫及橋頭部位不跳車。做完整的施工原始資料記錄。

監(jiān)理工作方法及措施為了保證工程最終能達(dá)到設(shè)計(jì)文件和技術(shù)規(guī)范的要求,對工程質(zhì)量實(shí)施有效的控制,應(yīng)該采取如下方法和措施:監(jiān)理程序控制:分項(xiàng)工程開工報(bào)告:每項(xiàng)橋梁開工之前,要求承包人提交分項(xiàng)工程報(bào)告進(jìn)行審批,開工報(bào)告應(yīng)提出工程實(shí)施計(jì)劃和施工方案,橋梁工程質(zhì)量控制指標(biāo)及檢驗(yàn)頻率和方法。說明材料、設(shè)備、勞力及現(xiàn)場管理人員等項(xiàng)的準(zhǔn)備情況;提供放樣測量、標(biāo)準(zhǔn)試驗(yàn)等必須的基礎(chǔ)資料。工序自檢報(bào)告:承包人的自檢人員應(yīng)按照專業(yè)監(jiān)理工程師批準(zhǔn)的工藝流程和提出的工藝檢

溫馨提示

  • 1. 本站所有資源如無特殊說明,都需要本地電腦安裝OFFICE2007和PDF閱讀器。圖紙軟件為CAD,CAXA,PROE,UG,SolidWorks等.壓縮文件請下載最新的WinRAR軟件解壓。
  • 2. 本站的文檔不包含任何第三方提供的附件圖紙等,如果需要附件,請聯(lián)系上傳者。文件的所有權(quán)益歸上傳用戶所有。
  • 3. 本站RAR壓縮包中若帶圖紙,網(wǎng)頁內(nèi)容里面會有圖紙預(yù)覽,若沒有圖紙預(yù)覽就沒有圖紙。
  • 4. 未經(jīng)權(quán)益所有人同意不得將文件中的內(nèi)容挪作商業(yè)或盈利用途。
  • 5. 人人文庫網(wǎng)僅提供信息存儲空間,僅對用戶上傳內(nèi)容的表現(xiàn)方式做保護(hù)處理,對用戶上傳分享的文檔內(nèi)容本身不做任何修改或編輯,并不能對任何下載內(nèi)容負(fù)責(zé)。
  • 6. 下載文件中如有侵權(quán)或不適當(dāng)內(nèi)容,請與我們聯(lián)系,我們立即糾正。
  • 7. 本站不保證下載資源的準(zhǔn)確性、安全性和完整性, 同時(shí)也不承擔(dān)用戶因使用這些下載資源對自己和他人造成任何形式的傷害或損失。

最新文檔

評論

0/150

提交評論