項(xiàng)目專項(xiàng)施工方案
洛陽(yáng)大河薈項(xiàng)目工程
鋼結(jié)構(gòu)專項(xiàng)施工方案
編制單位:
編制人:
日期:
項(xiàng)目專項(xiàng)施工方案
目錄
第一章編制依據(jù)........................................................................................................................................-1-
第二章工程概況........................................................................................................................................-2-
2.1工程建設(shè)概況............................................................................................................................-2-
2.2鋼結(jié)構(gòu)設(shè)計(jì)概況.......................................................................................................................-2-
2.3工程施工條件............................................................................................................................-3-
第三章施工安排......................................................................................................................................-4-
3.1施工組織機(jī)構(gòu)的建立..............................................................................................................-4-
3.2施工組織機(jī)構(gòu)框架..................................................................................................................-4-
3.3施工組織機(jī)構(gòu)的高效運(yùn)作保障措施..................................................................................-6-
3.4施工流水段劃分.......................................................................................................................-7-
3.5工程施工重點(diǎn)和難點(diǎn)分析及應(yīng)對(duì)措施................................................................................-7-
3.6構(gòu)件加工及配送.......................................................................................................................-7-
3.7機(jī)械選型.....................................................................................................................................-8-
第四章施工進(jìn)度計(jì)劃..........................................................................................................................-10-
第五章施工準(zhǔn)備與資源配置計(jì)劃....................................................................................................-11-
5.1勞動(dòng)力配置計(jì)劃.....................................................................................................................-11-
5.2吊裝構(gòu)件主要形式一覽表..................................................................................................-11-
5.3吊裝校正機(jī)具計(jì)劃................................................................................................................-11-
5.4測(cè)量計(jì)量?jī)x器配置計(jì)劃.......................................................................................................-12-
5.5技術(shù)復(fù)核和隱蔽驗(yàn)收計(jì)劃..................................................................................................-12-
第六章施工方法及工藝要求.............................................................................................................-13-
6.1鋼結(jié)構(gòu)加工工藝.....................................................................................................................-13-
6.1.1鋼結(jié)構(gòu)深化設(shè)計(jì)原則...............................................................................................-13-
深化設(shè)計(jì)組織機(jī)構(gòu).............................................................................................................-13-
深化設(shè)計(jì)工作方案.............................................................................................................-13-
6.2鋼結(jié)構(gòu)的加工制作................................................................................................................-13-
加工制作特點(diǎn)......................................................................................................................-14-
加工制作設(shè)備配置計(jì)劃....................................................................................................-14-
焊接材料選用與管理........................................................................................................-18-
6.2.4十字柱制作加工工藝...............................................................................................-21-
6.3鋼結(jié)構(gòu)施工方法.....................................................................................................................-29-
6.3.1安裝準(zhǔn)備工作.............................................................................................................-29-
6.3.2構(gòu)件的堆放.................................................................................................................-29-
6.3.3安裝輔助材料的準(zhǔn)備...............................................................................................-30-
6.4鋼結(jié)構(gòu)安裝流程及準(zhǔn)備.......................................................................................................-31-
6.5鋼柱、鋼梁吊裝工藝...........................................................................................................-32-
6.6具體施工方法.........................................................................................................................-32-
6.6.1鋼構(gòu)件的分段.............................................................................................................-33-
6.6.2吊機(jī)起吊能力分析...................................................................................................-35-
6.6.3鋼柱吊裝順序.............................................................................................................-35-
6.7鋼柱、鋼梁現(xiàn)場(chǎng)安裝..............................................................................................................-36-
6.7.1鋼結(jié)構(gòu)現(xiàn)場(chǎng)焊接..........................................................................................................-36-
6.7.2緊固件安裝.................................................................................................................-40-
6.7.3高強(qiáng)螺栓安裝.............................................................................................................-42-
6.8鋼結(jié)構(gòu)測(cè)量..............................................................................................................................-46-
6.8.1安裝測(cè)量控制的總則...............................................................................................-46-
6.8.2測(cè)量主要內(nèi)容及重難點(diǎn)..........................................................................................-46-
項(xiàng)目專項(xiàng)施工方案
6.8.3測(cè)量控制準(zhǔn)備工作...................................................................................................-47-
6.8.4平面控制網(wǎng)的建立...................................................................................................-47-
6.8.5預(yù)埋件的測(cè)量定位...................................................................................................-49-
6.9驗(yàn)收要求..................................................................................................................................-50-
6.9.1驗(yàn)收標(biāo)準(zhǔn)......................................................................................................................-50-
6.9.2驗(yàn)收程序......................................................................................................................-51-
6.9.3驗(yàn)收內(nèi)容......................................................................................................................-51-
6.9.4驗(yàn)收人員......................................................................................................................-53-
第七章材料與檢、試驗(yàn)管理.............................................................................................................-55-
7.1材料管理..................................................................................................................................-55-
7.1.1材料管理原則.............................................................................................................-55-
7.1.2材料與成品管理措施...............................................................................................-55-
7.2檢、試驗(yàn)管理.........................................................................................................................-56-
7.2.1檢、試驗(yàn)主要項(xiàng)目及指標(biāo)......................................................................................-56-
7.2.2檢測(cè)主要項(xiàng)目及指標(biāo)...............................................................................................-56-
7.2.3檢驗(yàn)與試驗(yàn)計(jì)劃........................................................................................................-58-
7.2.4試驗(yàn)流程與相關(guān)要求...............................................................................................-60-
第八章質(zhì)量管理計(jì)劃..........................................................................................................................-62-
8.1質(zhì)量管理體系.........................................................................................................................-62-
8.2質(zhì)量控制主要內(nèi)容................................................................................................................-62-
8.3關(guān)鍵與特殊過(guò)程.......................................................................................................................-63-
8.4質(zhì)量控制措施.........................................................................................................................-63-
8.4.1鋼構(gòu)件安裝質(zhì)量保障措施......................................................................................-63-
8.4.2鋼柱、鋼梁現(xiàn)場(chǎng)焊接保證措施.............................................................................-64-
8.4.3高強(qiáng)度螺栓施工保證措施......................................................................................-66-
8.4.4栓釘焊接質(zhì)量保證措施..........................................................................................-71-
8.5質(zhì)量事故應(yīng)急預(yù)案................................................................................................................-72-
8.5.1質(zhì)量事故風(fēng)險(xiǎn)性分析...............................................................................................-72-
8.5.2重要風(fēng)險(xiǎn)因素分析及對(duì)策......................................................................................-73-
8.5.3應(yīng)急準(zhǔn)備的基本要求...............................................................................................-74-
第九章安全管理計(jì)劃..........................................................................................................................-81-
9.1安全生產(chǎn)的一般防護(hù)措施..................................................................................................-81-
9.1.1個(gè)人防護(hù)措施.............................................................................................................-81-
9.1.2高空作業(yè)和高空墜物防護(hù)措施.............................................................................-82-
9.1.3臨時(shí)用電安全防護(hù)措施..........................................................................................-83-
9.2鋼結(jié)構(gòu)頻發(fā)事故的防范措施..............................................................................................-85-
9.2.1火災(zāi)傷害的防護(hù)措施...............................................................................................-85-
9.2.2機(jī)械傷害的防護(hù)措施...............................................................................................-85-
9.2.3鋼結(jié)構(gòu)吊裝坍塌、墜落事故保障措施...............................................................-87-
9.3針對(duì)本工程的特殊安全措施..............................................................................................-88-
9.3.1鋼掛籃的設(shè)置.............................................................................................................-88-
9.3.2垂直作業(yè)通道爬梯...................................................................................................-88-
9.3.3接火盆..........................................................................................................................-89-
9.4安全應(yīng)急預(yù)案.........................................................................................................................-90-
9.4.1安全應(yīng)急預(yù)案措施...................................................................................................-90-
9.4.2安全應(yīng)急預(yù)案具體內(nèi)容..........................................................................................-94-
第十章進(jìn)度管理及保證措施..........................................................................................................-100-
10.1工期目標(biāo).............................................................................................................................-100-
10.2工期控制措施....................................................................................................................-100-
項(xiàng)目專項(xiàng)施工方案
第十一章綠色施工及保證措施......................................................................................................-101-
11.1綠色施工原則....................................................................................................................-101-
11.2綠色施工總體框架...........................................................................................................-101-
11.3綠色施工保證措施...........................................................................................................-101-
第十二章成品保護(hù).............................................................................................................................-104-
12.1成品保護(hù)組織機(jī)構(gòu)...........................................................................................................-104-
12.2成品保護(hù)實(shí)施措施...........................................................................................................-104-
12.3工廠制作成品保護(hù)措施..................................................................................................-104-
12.4運(yùn)輸過(guò)程中成品保護(hù)措施.............................................................................................-105-
12.5現(xiàn)場(chǎng)搬運(yùn)及安裝成品保護(hù).............................................................................................-105-
第十三章新冠肺炎疫情防控措施.................................................................................................-106-
13.1總體目標(biāo).............................................................................................................................-106-
13.2組織管理.............................................................................................................................-106-
13.3工作要求.............................................................................................................................-108-
13.4施工中具體措施................................................................................................................-110-
13.5上報(bào)制度與責(zé)任追究.......................................................................................................-111-
13.6新型冠狀病毒感染肺炎定點(diǎn)上報(bào)聯(lián)系醫(yī)院..............................................................-112-
附件一:構(gòu)件清單........................................................................................................................-114-
附件二:深化圖紙........................................................................................................................-118-
項(xiàng)目專項(xiàng)施工方案
第一章編制依據(jù)
序號(hào)類別標(biāo)準(zhǔn)名稱標(biāo)準(zhǔn)編號(hào)
1《建筑結(jié)構(gòu)可靠性設(shè)計(jì)統(tǒng)一標(biāo)準(zhǔn)》GB50068-2018
2《建筑工程抗震設(shè)防分類標(biāo)準(zhǔn)》GB50223-2008
3《建筑結(jié)構(gòu)荷載規(guī)范》GB50009-2012
4《建筑抗震設(shè)計(jì)規(guī)范》GB50011-2010
5《鋼結(jié)構(gòu)設(shè)計(jì)標(biāo)準(zhǔn)》GB50017-2017
6《混凝土結(jié)構(gòu)設(shè)計(jì)規(guī)范》GB50010-2010
7《建筑設(shè)計(jì)防火規(guī)范》GB50016-2014
8《鋼結(jié)構(gòu)焊接規(guī)范》GB50661-2011
9《鋼結(jié)構(gòu)防火涂料》GB14907-2018
10《結(jié)構(gòu)用無(wú)縫鋼管》GB/T8162-2018
11技術(shù)規(guī)范《直縫電焊鋼管》GB/T13793-2016
12《焊接結(jié)構(gòu)用鑄鋼件》GB/T7659-2010
13《高層建筑混凝土結(jié)構(gòu)技術(shù)規(guī)程》JGJ3-2010
14《鋼結(jié)構(gòu)高強(qiáng)度螺栓連接技術(shù)規(guī)程》JGJ82-2011
15《建筑鋼結(jié)構(gòu)防腐蝕技術(shù)規(guī)程》JGJ/T251-2011
16《高層民用建筑鋼結(jié)構(gòu)技術(shù)規(guī)程》JGJ99-2015
17《鋼筋桁架樓承板》JG/T368-2012
18《組合結(jié)構(gòu)設(shè)計(jì)規(guī)范》JGJ138-2016
19《鋼管結(jié)構(gòu)技術(shù)規(guī)程》CECS280-2010
20《鑄鋼節(jié)點(diǎn)應(yīng)用技術(shù)規(guī)程》CECS235-2008
21《鋼結(jié)構(gòu)防火涂料應(yīng)用技術(shù)規(guī)程》T/CECS24-2023
質(zhì)量管理
22《鋼結(jié)構(gòu)工程施工質(zhì)量驗(yàn)收標(biāo)準(zhǔn)》GB50205-2023
規(guī)范
23本工程施工圖紙/
24其他河南省有關(guān)建筑工程安裝文明施工規(guī)范、標(biāo)準(zhǔn)/
25本工程施工組織設(shè)計(jì)文件/
-1-
項(xiàng)目專項(xiàng)施工方案
第二章工程概況
2.1工程建設(shè)概況
工程名稱工程性質(zhì)文旅綜合體
建設(shè)規(guī)模約12.9億工程地址
總占地面積103128.4㎡總建筑面積190440.78m2
建設(shè)單位項(xiàng)目承包范圍鋼結(jié)構(gòu)工程制作安裝
設(shè)計(jì)單位主要分包工程鋼結(jié)構(gòu)工程
勘察單位質(zhì)量合格
合同
監(jiān)理單位工期60日歷天
要求
總承包單位安全安全生產(chǎn)零事故
地上部分為商業(yè)開(kāi)發(fā),含主題商業(yè)、休閑娛樂(lè)、特色餐飲、酒店、創(chuàng)新
工程主要功
辦公、文化演藝等多業(yè)態(tài)建筑;地下部分二層,功能為地下商業(yè)、充電
能或用途
站、人防和地下停車場(chǎng)等
2.2鋼結(jié)構(gòu)設(shè)計(jì)概況
本工程結(jié)構(gòu)形式為框架結(jié)構(gòu),主鋼構(gòu)勁性梁柱采用焊接H型、╋字型截面。
鋼柱、鋼梁材質(zhì)均為Q355-B,基礎(chǔ)柱腳連接形式為螺栓連接。
所屬區(qū)段勁鋼類型截面規(guī)格所處標(biāo)高范圍
2#樓H勁鋼柱H700*440*36*36基礎(chǔ)頂~-0.050m(1層)
2#樓十字柱十700*400*30*36基礎(chǔ)頂~-0.050m(1層)
2#樓十字柱十600/500*300*30*36基礎(chǔ)頂~+9.550m(3層)
2#樓十字柱十800*400*30*60基礎(chǔ)頂~-0.050m(1層)
2#樓十字柱十800/500*400/300*30*60*36基礎(chǔ)頂~+9.550m(3層)
2#樓十字柱十700/500*400/300*30*60-0.050~+9.550m(3層)
2#樓H勁鋼柱H300*250*36*36-0.050~5.650m(2層)
2#樓十字柱十300*150*20*30-0.050~5.650m(2層)
2#樓十字柱十800/500*400/300*30*60/36-0.050~+9.550m(3層)
2#樓H型梁H1650*400*30*55-0.050
2#樓H型梁H1250*400*30*36-0.050
2#樓H型梁H750*350*20*30-0.050
2#樓H型梁H1400*350*20*30-0.050
2#樓H型梁H650*300*20*30-0.050
2#樓H型梁H400*300*20*30-0.050
2.3工程施工條件
本工程位于洛陽(yáng)市洛龍區(qū)龍門交通樞紐公路客運(yùn)站西側(cè),通衢路以南,站前
-2-
項(xiàng)目專項(xiàng)施工方案
西路以北,金城寨街以東,永泰街以西,通車方便,可實(shí)現(xiàn)施工材料、設(shè)備快速
到達(dá)施工現(xiàn)場(chǎng)。
-3-
項(xiàng)目專項(xiàng)施工方案
第三章施工安排
3.1施工組織機(jī)構(gòu)的建立
在組建本工程項(xiàng)目管理班子時(shí),我公司將選派曾施工過(guò)類似本工程結(jié)構(gòu)形式
的具有豐富施工經(jīng)驗(yàn)的項(xiàng)目管理班子進(jìn)駐現(xiàn)場(chǎng)直接參與本工程的建設(shè)和管理。
根據(jù)本工程的規(guī)模和特點(diǎn),項(xiàng)目管理擬定采用直線職能式的總體項(xiàng)目管理組
織機(jī)構(gòu)—現(xiàn)場(chǎng)項(xiàng)目管理組織機(jī)構(gòu)的模式。
洛陽(yáng)大河薈項(xiàng)目作為一項(xiàng)影響較大的重點(diǎn)工程,我公司上至領(lǐng)導(dǎo),下至基層
施工人員,都對(duì)建好本工程有各方面的信心和決心,針對(duì)該工程的重要性,成立
洛陽(yáng)大河薈項(xiàng)目鋼結(jié)構(gòu)工程項(xiàng)目部,項(xiàng)目部對(duì)工程全面管理。
3.2施工組織機(jī)構(gòu)框架
明確各個(gè)部門的職責(zé)與權(quán)限,確保整個(gè)工程的順利進(jìn)行。施工現(xiàn)場(chǎng)實(shí)行項(xiàng)目
經(jīng)理負(fù)責(zé)制及各級(jí)分管負(fù)責(zé)制,項(xiàng)目經(jīng)理集責(zé)、權(quán)、利于一身,解決發(fā)生在工程
施工過(guò)程中的所有問(wèn)題。遇到問(wèn)題,報(bào)總公司總工辦,協(xié)同業(yè)主、監(jiān)理單位一同
解決。
統(tǒng)一建立工作標(biāo)準(zhǔn),用建立的標(biāo)準(zhǔn)衡量當(dāng)前的工作。分析偏差產(chǎn)生的原因,
及時(shí)采取補(bǔ)救措施。控制的主要內(nèi)容包括進(jìn)度、費(fèi)用和工程質(zhì)量等,采取定期不
定期的工作檢查,力爭(zhēng)使實(shí)際情況與控制標(biāo)準(zhǔn)之間的偏差減少到最低限度,確保
項(xiàng)目目標(biāo)的圓滿實(shí)現(xiàn)。
(1)現(xiàn)場(chǎng)項(xiàng)目經(jīng)理部
現(xiàn)場(chǎng)項(xiàng)目管理組織機(jī)構(gòu)框架
項(xiàng)目經(jīng)理
項(xiàng)目副經(jīng)理
項(xiàng)目技術(shù)負(fù)責(zé)人項(xiàng)目生產(chǎn)經(jīng)理
深施質(zhì)制財(cái)資綜
化工量造務(wù)料合
設(shè)管安部部部管
計(jì)理全(理
部部文檔部
((明案
技工管室
術(shù)程理)
部部部
))
材構(gòu)車檢結(jié)測(cè)焊質(zhì)安
料件隊(duì)測(cè)構(gòu)量接量全
采加試吊校組管文
購(gòu)工驗(yàn)裝正理明
組組組組組組管
理
-4-
項(xiàng)目專項(xiàng)施工方案
現(xiàn)場(chǎng)組織管理機(jī)構(gòu)的職責(zé)
1、本工程項(xiàng)目管理方法采取分層次管理:
序號(hào)分層次管理方法
第一級(jí)管理由業(yè)主、監(jiān)理單位組成的總項(xiàng)目部,對(duì)我們現(xiàn)場(chǎng)具體實(shí)施情況進(jìn)行
1
宏觀監(jiān)控,通過(guò)每周召開(kāi)高層次協(xié)調(diào)例會(huì)和現(xiàn)場(chǎng)巡視,制定宏觀計(jì)劃目標(biāo)。
第二級(jí)管理主要由我公司項(xiàng)目部進(jìn)行,提出實(shí)現(xiàn)計(jì)劃的措施,組織和協(xié)調(diào)項(xiàng)目
的全方位實(shí)施的決定。貫徹決策層的決定和指令,修訂項(xiàng)目計(jì)劃,確定工藝流
2
程,協(xié)調(diào)交叉施工的矛盾,解決施工過(guò)程中遇到的問(wèn)題,每日控制施工計(jì)劃進(jìn)
度和工程質(zhì)量,保證各階段目標(biāo)實(shí)現(xiàn)。
組織結(jié)構(gòu)圖中的項(xiàng)目經(jīng)理由本公司總經(jīng)理任命并授權(quán),對(duì)整個(gè)項(xiàng)目的實(shí)施負(fù)
3
責(zé)。
2、項(xiàng)目經(jīng)理職責(zé)
序號(hào)管理職責(zé)
工程的項(xiàng)目負(fù)責(zé)人,第一責(zé)任人,負(fù)責(zé)工程的質(zhì)量、進(jìn)度和安全文明生產(chǎn)、與
1
本項(xiàng)目各專業(yè)工程施工單位的協(xié)調(diào)配合等。
2組織編制項(xiàng)目質(zhì)量計(jì)劃,使整個(gè)項(xiàng)目按照ISO9001標(biāo)準(zhǔn)體系運(yùn)作。
3主持編制項(xiàng)目管理方案,確定項(xiàng)目管理的目標(biāo)和方針。
確定項(xiàng)目部組織機(jī)構(gòu)配備人員,制定規(guī)章制度,明確有關(guān)人員的職責(zé),組織項(xiàng)
4
目部開(kāi)展工作。
及時(shí)、適當(dāng)?shù)刈龀鲰?xiàng)目管理決策,其主要內(nèi)容包括投標(biāo)報(bào)價(jià)決策、分包選擇決
5
策、重大技術(shù)方案決策、合同簽訂及變更決策等。
與業(yè)主、監(jiān)理保持經(jīng)常接觸,解決隨機(jī)出現(xiàn)的各種問(wèn)題,替業(yè)主、監(jiān)理排憂解
6
難,確保業(yè)主利益。
3、項(xiàng)目副經(jīng)理職責(zé)
序號(hào)管理職責(zé)
直接領(lǐng)導(dǎo)技術(shù)部,組織項(xiàng)目的技術(shù)質(zhì)量工作,審核項(xiàng)目施工組織與施工方案,
1
并解決各方面的技術(shù)質(zhì)量問(wèn)題。
具體主持項(xiàng)目質(zhì)量管理保證體系的建立,并進(jìn)行質(zhì)量職能分配,落實(shí)質(zhì)量責(zé)任
2制,確定項(xiàng)目質(zhì)量記錄及項(xiàng)目的關(guān)鍵過(guò)程和特殊過(guò)程,并確定相應(yīng)的技術(shù)參數(shù)
和實(shí)施措施及決策。
-5-
項(xiàng)目專項(xiàng)施工方案
3與設(shè)計(jì)、監(jiān)理保持溝通,保證設(shè)計(jì)、監(jiān)理的要求與指令得以貫徹實(shí)施。
組織專家顧問(wèn)組對(duì)本項(xiàng)目的關(guān)鍵技術(shù)難題進(jìn)行科研攻關(guān),進(jìn)行新工藝、新技術(shù)
4
的研究,確保本項(xiàng)目順利進(jìn)行。
4、項(xiàng)目總工程師職責(zé)(項(xiàng)目技術(shù)負(fù)責(zé)人)
序號(hào)管理職責(zé)
直接領(lǐng)導(dǎo)技術(shù)部,組織項(xiàng)目的技術(shù)質(zhì)量工作,審核項(xiàng)目施工組織與施工方案,
1
并解決各方面的技術(shù)質(zhì)量問(wèn)題。
具體主持項(xiàng)目質(zhì)量管理保證體系的建立,并進(jìn)行質(zhì)量職能分配,落實(shí)質(zhì)量責(zé)任
2制,確定項(xiàng)目質(zhì)量記錄及項(xiàng)目的關(guān)鍵過(guò)程和特殊過(guò)程,并確定相應(yīng)的技術(shù)參數(shù)
和實(shí)施措施及決策。
3與設(shè)計(jì)、監(jiān)理保持溝通,保證設(shè)計(jì)、監(jiān)理的要求與指令得以貫徹實(shí)施。
組織專家顧問(wèn)組對(duì)本項(xiàng)目的關(guān)鍵技術(shù)難題進(jìn)行科研攻關(guān),進(jìn)行新工藝、新技術(shù)
4
的研究,確保本項(xiàng)目順利進(jìn)行。
5、鋼結(jié)構(gòu)制作主管職責(zé)
序號(hào)管理職責(zé)
1負(fù)責(zé)組織鋼結(jié)構(gòu)的二次深化設(shè)計(jì)工作,對(duì)詳圖的深化設(shè)計(jì)管理。
2動(dòng)態(tài)管理深化設(shè)計(jì)的計(jì)劃進(jìn)度,確保本工程深化設(shè)計(jì)工作如期完成。
3負(fù)責(zé)鋼結(jié)構(gòu)材料的生產(chǎn)加工制作,進(jìn)行材料采購(gòu),制定生產(chǎn)計(jì)劃。
4負(fù)責(zé)加工的工藝管理及生產(chǎn)質(zhì)量控制。
5負(fù)責(zé)構(gòu)件的運(yùn)輸。
6、鋼結(jié)構(gòu)安裝主管職責(zé)
序號(hào)管理職責(zé)
1負(fù)責(zé)本工程現(xiàn)場(chǎng)施工的技術(shù)組織工作。
動(dòng)態(tài)管理計(jì)劃進(jìn)度,管好材料計(jì)劃、勞動(dòng)力計(jì)劃、機(jī)械調(diào)配計(jì)劃,確保工程如
2
期完成。
3負(fù)責(zé)項(xiàng)目的安全施工,領(lǐng)導(dǎo)安全管理組織體系,確保施工無(wú)重大安全事故。
4施工協(xié)調(diào),解決各部門在施工過(guò)程的矛盾。
具體抓好項(xiàng)目的進(jìn)度管理,從計(jì)劃進(jìn)度、實(shí)際進(jìn)度和進(jìn)度調(diào)整等多方面進(jìn)行控
5
制,確保項(xiàng)目如期完成。
6分析、預(yù)測(cè)工程總成本及階段成本,確保工程項(xiàng)目的資金合理流轉(zhuǎn)。
3.3施工組織機(jī)構(gòu)的高效運(yùn)作保障措施
項(xiàng)目經(jīng)理與企業(yè)法人代表是項(xiàng)目的代表人,全權(quán)負(fù)責(zé)履行工程合同,對(duì)工程
的工期、質(zhì)量、安全、成本等全面領(lǐng)導(dǎo),故項(xiàng)目經(jīng)理在本工程的施工全過(guò)程中,
原則上不離開(kāi)本項(xiàng)目,投標(biāo)人承諾不經(jīng)業(yè)主同意,決不擅自撤換項(xiàng)目經(jīng)理,為了
保證施工管理的連續(xù)性,項(xiàng)目其他主要管理人員不經(jīng)業(yè)主同意,原則上也不予撤
-6-
項(xiàng)目專項(xiàng)施工方案
換。
3.4施工流水段劃分
根據(jù)總包的施工平面布置和施工計(jì)劃,按照區(qū)段劃分進(jìn)行分段施工
3.5工程施工重點(diǎn)和難點(diǎn)分析及應(yīng)對(duì)措施
十字型鋼柱、H型鋼梁的工廠制作焊接量比較大,制作工藝相對(duì)復(fù)雜。
編號(hào)重點(diǎn)內(nèi)容解決策略
構(gòu)件截面較制定合理焊接方案及措施,建立健全焊接質(zhì)量保證體系,制定
1大,焊接變形科學(xué)合理的技術(shù)路線,制定合理的焊接工藝書(shū),減少焊接變形
控制較難和焊接殘余應(yīng)力,從而有效的控制焊接變形。
鋼梁等構(gòu)件的孔眼位置加工也必須精確無(wú)誤,方能為施工提供保
構(gòu)件尺寸及鉆
2障,主要通過(guò)完善的加工工藝和先進(jìn)的加工設(shè)備來(lái)加以保證。同
孔加工精度高
時(shí)公司采取單元預(yù)拼裝措施來(lái)檢驗(yàn),保證出廠構(gòu)件的加工精度。
制定合理的加工工藝,在鋼柱的組對(duì)及焊接過(guò)程中要嚴(yán)格按照
鋼柱需現(xiàn)場(chǎng)二
要求在專用胎架上進(jìn)行,并在胎架上事先畫(huà)出組對(duì)尺寸控制
3次拼裝,制作
線,組對(duì)完成后對(duì)尺寸進(jìn)行復(fù)核,發(fā)現(xiàn)問(wèn)題立即整改修復(fù),焊
的精度要求
接過(guò)程中要有效的避免焊接變形。
采用合理的焊接順序,先焊收縮量較大的焊縫,應(yīng)盡量保證構(gòu)
焊接殘余應(yīng)力
4件的另一端有自由收縮的余地。對(duì)于個(gè)別典型復(fù)雜節(jié)點(diǎn)應(yīng)力比
的控制
較集中,焊后也可采用局部熱處理或整體熱處理。
施工場(chǎng)地緊與加工廠充分協(xié)調(diào),給加工廠提供詳細(xì)合理的構(gòu)件進(jìn)場(chǎng)清單
5促,材料構(gòu)件表,確保鋼構(gòu)件合理的供貨。在工程施工的不同階段,根據(jù)該
堆場(chǎng)十分有限階段現(xiàn)場(chǎng)情況,對(duì)鋼構(gòu)件施工現(xiàn)場(chǎng)堆放進(jìn)行合理規(guī)劃布置。
采取“管理高目標(biāo),質(zhì)量高標(biāo)準(zhǔn),專業(yè)細(xì)配合,過(guò)程嚴(yán)控制,
本工程施工工計(jì)劃細(xì)安排,設(shè)備早訂貨,專款專使用”的原則進(jìn)行總體施工
6
期比較緊張組織;選擇與本公司達(dá)成施工意向的并長(zhǎng)期與公司合作、有豐
富施工經(jīng)驗(yàn)和雄厚技術(shù)實(shí)力的勞務(wù)公司,以加快現(xiàn)場(chǎng)施工。
3.6構(gòu)件加工及配送
本工程所有構(gòu)件均是在鄭州誠(chéng)信鋼結(jié)構(gòu)有限公司加工廠內(nèi)進(jìn)行加工,它位于
河南省新鄉(xiāng)市原陽(yáng)縣城關(guān)鎮(zhèn)太行大道與萬(wàn)象路口東300米路北,構(gòu)件運(yùn)輸路線如
下圖所示。
-7-
項(xiàng)目專項(xiàng)施工方案
圖3.6-1構(gòu)件配送路線圖
3.7機(jī)械選型
考慮現(xiàn)場(chǎng)場(chǎng)地情況,結(jié)合構(gòu)件特點(diǎn),機(jī)械選型按以下原則選?。罕竟こ啼摌?gòu)
件可分為三類:一類為十字型鋼柱,一類為H型鋼柱,一類為H型鋼梁。由于鋼
柱、鋼梁重量比較大,結(jié)合現(xiàn)場(chǎng)情況、運(yùn)輸及吊裝能力,鋼柱分段分節(jié)進(jìn)行吊裝,
標(biāo)高-0.05m以下采用25噸汽車吊,待基礎(chǔ)筏板澆筑完成后進(jìn)行安裝,標(biāo)高-0.05m
以上十字柱、H字柱待標(biāo)高-0.05m層樓面板澆筑完成后,采用ZTT6517塔吊安裝。
圖3.7-125噸汽車吊性能表(STC250)
-8-
項(xiàng)目專項(xiàng)施工方案
圖3.7-2ZTT6517塔吊載荷特性性能表
-9-
項(xiàng)目專項(xiàng)施工方案
第四章施工進(jìn)度計(jì)劃
根據(jù)本工程的工期要求及計(jì)劃,鋼結(jié)構(gòu)施工計(jì)劃2023年04月03日開(kāi)始施
工,2023年5月25日施工完成,工期約52日歷天。具體實(shí)施依據(jù)現(xiàn)場(chǎng)情況確
定。
-10-
項(xiàng)目專項(xiàng)施工方案
第五章施工準(zhǔn)備與資源配置計(jì)劃
5.1勞動(dòng)力配置計(jì)劃
由于本工程工期較緊,因此要求現(xiàn)場(chǎng)安裝人員數(shù)量必須滿足各工作面趕工要
求,特種作業(yè)人員必須持證上崗,同時(shí)對(duì)施工人員必須全覆蓋進(jìn)行事前有針對(duì)性
的技術(shù)培訓(xùn)與交底,確保各工種施工人員能夠勝任崗位職責(zé),不違章作業(yè)。
工種人數(shù)工種人數(shù)
技術(shù)管理人員3人安全管理人員1人
電焊工4人
溫馨提示
- 1. 本站所有資源如無(wú)特殊說(shuō)明,都需要本地電腦安裝OFFICE2007和PDF閱讀器。圖紙軟件為CAD,CAXA,PROE,UG,SolidWorks等.壓縮文件請(qǐng)下載最新的WinRAR軟件解壓。
- 2. 本站的文檔不包含任何第三方提供的附件圖紙等,如果需要附件,請(qǐng)聯(lián)系上傳者。文件的所有權(quán)益歸上傳用戶所有。
- 3. 本站RAR壓縮包中若帶圖紙,網(wǎng)頁(yè)內(nèi)容里面會(huì)有圖紙預(yù)覽,若沒(méi)有圖紙預(yù)覽就沒(méi)有圖紙。
- 4. 未經(jīng)權(quán)益所有人同意不得將文件中的內(nèi)容挪作商業(yè)或盈利用途。
- 5. 人人文庫(kù)網(wǎng)僅提供信息存儲(chǔ)空間,僅對(duì)用戶上傳內(nèi)容的表現(xiàn)方式做保護(hù)處理,對(duì)用戶上傳分享的文檔內(nèi)容本身不做任何修改或編輯,并不能對(duì)任何下載內(nèi)容負(fù)責(zé)。
- 6. 下載文件中如有侵權(quán)或不適當(dāng)內(nèi)容,請(qǐng)與我們聯(lián)系,我們立即糾正。
- 7. 本站不保證下載資源的準(zhǔn)確性、安全性和完整性, 同時(shí)也不承擔(dān)用戶因使用這些下載資源對(duì)自己和他人造成任何形式的傷害或損失。
最新文檔
- 深化中心策略落實(shí)加強(qiáng)管理規(guī)范
- 2024年中國(guó)聯(lián)通西安市分公司招聘真題
- 2024年寶雞高新區(qū)招聘幼兒園教職工真題
- 2025年輕微型無(wú)人機(jī)考試題庫(kù)含完整答案詳解【易錯(cuò)題】
- 兒科知識(shí)業(yè)務(wù)學(xué)習(xí)考試題(含答案)
- 2024年中醫(yī)執(zhí)業(yè)醫(yī)師醫(yī)技能力繼續(xù)教育考試題庫(kù)(附含答案)
- 2025年注冊(cè)測(cè)繪師法律法規(guī)真題及答案
- 2024年山西省“安全生產(chǎn)月”知識(shí)競(jìng)賽試題附參考答案
- 2025-2030中國(guó)煤矸石標(biāo)磚行業(yè)市場(chǎng)運(yùn)營(yíng)模式及未來(lái)發(fā)展動(dòng)向預(yù)測(cè)報(bào)告
- 2024年(綜合監(jiān)控系統(tǒng))通信網(wǎng)絡(luò)運(yùn)行管理員專業(yè)知識(shí)試題與答案
- 08J333 建筑防腐蝕構(gòu)造
- DL∕ T 802.7-2010 電力電纜用導(dǎo)管技術(shù)條件 第7部分:非開(kāi)挖用改性聚丙烯塑料電纜導(dǎo)管
- 香港朗文1A-6B全部單詞(音標(biāo)版)
- CJJ57-2012 城鄉(xiāng)規(guī)劃工程地質(zhì)勘察規(guī)范
- JT-T-325-2018營(yíng)運(yùn)客運(yùn)類型劃分及等級(jí)評(píng)定
- 入廠燃料驗(yàn)收管理驗(yàn)收統(tǒng)一標(biāo)準(zhǔn)
- 2024年03月新疆烏魯木齊海關(guān)所屬事業(yè)單位招考聘用14人筆試歷年典型考題及考點(diǎn)研判與答案解析
- 2017智慧樹(shù)創(chuàng)意學(xué)經(jīng)濟(jì)期末考試答案
- DZ∕T 0273-2015 地質(zhì)資料匯交規(guī)范(正式版)
- 臨滄市市級(jí)單位遴選(選調(diào))筆試真題2021
- 急性重癥胰腺炎治療指南
評(píng)論
0/150
提交評(píng)論